27.4  Rectification of Defects in the Works 

During the Development Phase, Project Co must promptly rectify all Defects in the Works as soon as they are identified, unless the Defect is:

(a)  a Technical Acceptance Outstanding Item included in a Technical Acceptance Outstanding Items List in accordance with clause 22.4, in which case Project Co's obligations to rectify the Technical Acceptance Outstanding Item are set out in clause 22.4(f)

(b)  included in the Remaining Works Schedule, in which case Project Co's obligations to rectify the Defect are set out in clause 24.3(l);

(c)  a Returned Works Outstanding Item in which case Project Co's obligations to rectify the Defect are set out in clause 24.4(n)(iv); or

(d)  a Defect which the State accepts or rectifies in accordance with clause 27.6(a).