27.4  Rectification of Defects in the Works 

During the Development Phase, Project Co must promptly rectify all Defects in the Works as soon as they are identified, unless the Defect is:

(a)  a Technical Acceptance Outstanding Item included in a Technical Acceptance Outstanding Items List in accordance with clause 22.4, in which case Project Co's obligations to rectify the Technical Acceptance Outstanding Item are set out in clause 22.4(f); 

(b)  included in the Remaining Works Schedule, in which case Project Co's obligations to rectify the Defect are set out in clause 24.3(l);

(c)  a Returned Works Outstanding Item in which case Project Co's obligations to rectify the Defect are set out in clause 24.4(n)(iv); or

(d)  a Defect which the State accepts or rectifies in accordance with clause 27.6(a).