To the extent that the conditions precedent in clause 32.1(c) have been satisfied, then:
(a) (suspension): the relevant obligations of Project Co will be suspended, but only until the earlier of the date the Intervening Event and its consequences cease to prevent Project Co from performing the Services or other obligations under this Deed (which are not Development Activities), or would have ceased to prevent Project Co from performing the Services or other obligations under this Deed (which are not Development Activities) had Project Co or any Project Co Associate not failed to do any of the things contemplated by clause 43.10(a)(ii); and
(b) (no breach): the failure to perform such suspended obligations will not be a Default, a Project Co Act or Omission, a Major Default, a Default Termination Event or a Performance Failure.