(a) (Modification Request): Without limiting its rights under clause 35.10, the State may, at any time, issue to Project Co, a notice entitled "Modification Request" for a Modification which must include details of:
(i) the proposed Modification which the State is considering;
(ii) the State's preferred funding, if any is required, for the proposed Modification in accordance with the Change Compensation Principles; and
(iii) any specific information that the State requires Project Co to include in its Change Notice or that may be relevant to the preparation of the Change Notice,
(b) (No obligation to proceed): The State will not be obliged to proceed with any Modification proposed in a Modification Request.