Within [10] Business Days after the State's receipt of Project Co's Modification Proposal, the State and Project Co must meet to discuss the Modification Proposal and may agree:
(a) (agreement and issue of a Change Response): Project Co's or the State's entitlement in respect of the relevant Modification, in which case the State must issue a Change Response in accordance with that agreement and otherwise in accordance with clause 35.5 and the Change Compensation Principles;
(b) (alternative process may apply): an alternative process for determining Project Co's or the State's entitlement in respect of the Modification;
(c) (changes to Modification Proposal): any changes that are to be made to the Modification Proposal;
(d) (further information): the process for Project Co to provide any further information in respect of the Modification Proposal; or
(e) (other matters): anything else relevant to the Modification Proposal or Modification.