Project Co must:
(a) (access to be granted): grant such access rights as are necessary and take all action that is necessarily required by the State to assist the State in exercising its rights under clause 38.2;
(b) (sufficient resources): provide sufficient resources, including personnel, to assist the State in exercising its rights under clause 38.2; and
(c) (not hinder): not do anything to hinder, disrupt or prevent the State in exercising its rights under clause 38.2.