Section 2 - Details of the effect of the relevant Change Compensation Event

To the extent known or able to be predicted, Project Co considers that the Change Notice Event will have the following effects on:

• The workmanship, quality, appearance or durability of any part of the Project:

[insert details]

• The design, manufacture, construction, supply, installation, or commissioning of the Works:

[insert details]

• The management and maintenance of the Project Assets:

[insert details]

• The carrying out of the Services and Project Co's ability to carry out Services in accordance with the Operational Phase Requirements:

[insert details]

• The use of the Project Assets and the safe, efficient and continuous operation of the Project Assets:

[insert details]

• The Project Assets meeting the FFP Warranty:

[insert details]

• Any other warranties given by Project Co in the Project Deed:

[insert details]

• Any relevant part of the Project Deed, including any amendments required:

[insert details]

• The performance of any other obligations of Project Co under the Project Documents:

[insert details]

• Any existing Approvals or the requirements for any new Approvals:

[insert details]

• Any damage caused by the Change Notice Event:

[insert details]