6.2  Relevant Approvals to be obtained and complied with by Project Co

(a)  (Project Co to obtain Approvals (other than State Approvals)): Project Co must:

(i)  obtain all Approvals (other than the State Approvals); 

(ii)  maintain all Approvals; and

(iii)  subject to clause 6.1(b), obtain any amendments to any Approvals.

(b)  (Project Co to obtain secondary approvals): Project Co must:

(i)  obtain all secondary consents, verifications and information; and

(ii)  undertake other action,

required under a State Approval unless otherwise required to be satisfied or fulfilled by the State in accordance with Attachment 2.

(c)  (Project Co to comply): Project Co must not take or fail to take (as the case may be) any action that will prevent the State from complying with, to the extent relevant, any conditions or requirements of any Approval or Environmental Requirement.

(d)  (Deviations from the approved Project): If the Project, as proposed or undertaken by Project Co, deviates from the Project that is permitted by and will comply with the State Approvals, Project Co must, subject to clause 6.1(b), obtain and comply with any:

(i)  further Approvals required as a result of such deviation; and

(ii)  necessary amendments to Approvals (including, to the extent necessary, the State Approvals).

(e)  (Copies of Approvals): Project Co must promptly provide to the State:

(i)  copies of all Approvals that it is required to obtain under any State Project Document when they are obtained, amended or renewed; and

(ii)  upon request, evidence that Project Co has complied with any conditions or requirements of the Approvals.

(f)  (Condition precedent): Project Co must, as a condition precedent to Commercial Acceptance, ensure that it has:

(i)  obtained all Approvals that it is required to obtain under this Deed with respect to the Works; and

(ii)  complied with, carried out and fulfilled all conditions and requirements of all Approvals with respect to the Works.