(a) (Notify the State of all Subcontractors): Project Co must provide the State with notice of:
(i) each proposed Key Subcontractor and Significant Subcontractor and any other Subcontractor engaged by a Key Subcontractor, 20 Business Days prior to; and
(ii) any other Subcontractor, 1 Business Day prior to,
their engagement to perform any of the Project Activities, provided that clause 9.2(a)(i) will not apply to the Management Services Contractor or any Key Subcontractor or Significant Subcontractor who, as at the date of this Deed, has already been selected by Project Co and named in the Contract Particulars.
(b) (Subcontracting requirements): Without limiting clause 9.3, Project Co must not engage, and must ensure that none of its:
(i) Key Subcontractors engage, any Subcontractor unless the State, within 15 Business Days after receipt of notification under clause 9.2(a), does not require a Probity Investigation to be carried out in respect of that Subcontractor; and
(ii) Key Subcontractors or Significant Subcontractors engage any Subcontractor, unless the proposed Subcontractor has the financial capacity, experience and capability to perform the obligations of Project Co to be subcontracted to the Subcontractor to at least the standards required by the State Project Documents. [Note: Subject to Project Co's subcontracting structure.]
(c) (Copies of Subcontracts): Project Co:
(i) must provide to the State:
A. a copy of any Key Subcontract, Significant Subcontract and Management Services Contract no later than 10 Business Days prior to the date on which Project Co proposes to enter into the relevant Key Subcontract, Significant Subcontract or Management Services Contract (as the case may be);
B. a copy of any Key Subcontract, Significant Subcontract and Management Services Contract within 15 Business Days after the relevant Subcontract is entered into; and
C. a copy of any other Subcontract requested by the State to which Project Co or a Key Subcontractor, Subcontractor to a Key Subcontractor or Significant Subcontractor has access or, to which a prudent, competent and experienced person in the position of Project Co, the Key Subcontractor, the Subcontractor to a Key Subcontractor or a Significant Subcontractor exercising Best Industry Practices would have access, within 15 Business Days after any request by the State; and
(ii) other than in respect of the Key Subcontracts and Management Services Contract, may redact any commercially sensitive information from any Subcontract provided under clause 9.2(c)(i) before it is provided to the State.