(a) (Project Co to ensure competence): Project Co must ensure that all persons employed or engaged to perform the Project Activities hold appropriate qualifications and have received appropriate training for their intended duties, and provide evidence of such qualifications and training to the State as reasonably requested.
(b) (Incompetence): If the State notifies Project Co that, in the State's reasonable opinion, any person employed or engaged on the Project Activities is incompetent, does not meet the standard required by clause 9.4(a), or is negligent, dishonest or guilty of misconduct, then, without limiting Project Co's other obligations under this Deed, Project Co must promptly ensure that such person is removed from performing any Project Activities for the remainder of the Project.