11.4  Traffic management

(a)  (Traffic management): Subject to the Road Management Act, the Relevant Legislation and the powers and functions of any relevant road authority under the Road Management Act, Project Co must, and must ensure that the Project Co Associates (as applicable), during the carrying out of the Project Activities, manage all traffic on, and to and from, the Project Area (as the case may be) but only to the extent affected by those Project Activities to ensure:

(i)  the safe, efficient and continuous movement of traffic;

(ii)  that any traffic congestion, delays or disruptions to roads, public transport, pedestrians, cyclists, or any shared use path are minimised; and

(iii)  that Project Co otherwise complies with the requirements of this Deed.

(b)  (Compliance): Project Co must:

(i)  at all times when performing the Project Activities comply with the Traffic Management Strategy, Road Management Act, Relevant Legislation, the Road Safety Act 1986 (Vic) and the requirements of this Deed in connection with traffic management; and

(ii)  comply with the directions of the State and any relevant road authority under the Road Management Act in connection with the management of traffic.

[Note: Traffic management systems may be considered on a project specific basis.]