(a) (Contamination Compensation Event): To the extent that Project Co is required to Remediate Contamination in accordance with clause 11.6(e)(v) or clause 11.6(e)(vi) (Contamination Compensation Event), this will be deemed to be a Modification in respect of which Project Co may submit a Modification Proposal in accordance with clause 35.2(a)(iii) and Project Co's entitlements will be determined in accordance with clause 35 and the Change Compensation Principles as if the Contamination Compensation Event was a State Initiated Modification .
(b) (Conditions for Project Co Claim): Project Co is not entitled to make any Claim against the State in respect of any Contamination Compensation Event (including its impact) unless it has given notice under clause 11.6(b) and clause 35.2(a)(iii).
[Note: Definition of Contamination Compensation Event must be considered on a project specific basis, having regard to the Project Area.]