(a) (FFP obligation): Project Co must design the Project Assets and develop the Design Documentation in accordance with the Delivery Requirements and so that the Project Assets, when manufactured or constructed in accordance with the Construction Documentation will satisfy the relevant FFP Warranty.
(b) (Design Development Process): Project Co must:
(i) prepare the Design Documentation; and
(ii) submit it for review by the Independent Reviewer and the State,
in accordance with the design development process set out in the Delivery Requirements (Design Development Process).
(c) (No Claim): The Design Development Process itself does not constitute a Modification and Project Co is not entitled to make any Claim against the State or any State Associate for any Liabilities suffered or incurred by Project Co in connection with the conduct of the Design Development Process.