Project Co must undertake the Works:
(a) (Construction requirements): in accordance with:
(i) the PSDR;
(ii) the Construction Documentation; and
(iii) the other requirements of this Deed; and
(b) (standard): so that:
(i) the Maintained Assets, Remaining Works and Returned Assets satisfy the relevant FFP Warranty;
(ii) the Temporary Works are Fit for Purpose; and
(iii) the Maintained Assets are wholly located within the area identified in the Operational Phase Area Plan. [Note: To be considered further on a project specific basis.]