26.7  Change Notice

To claim an extension of time to the relevant Date for Acceptance under this Deed, Project Co must submit a Change Notice for that Extension Event, to the State and the Independent Reviewer no later than 20 Business Days after the earlier of the date on which Project Co:

(a)  (became aware of delay): first became aware of the relevant delay to Project Co achieving Acceptance; or

(b)  (ought to have become aware): ought reasonably to have become aware of the relevant delay to Project Co achieving Acceptance,

in accordance with the Change Compensation Principles and must continue to update the State and the Independent Reviewer in respect of the Extension Event in accordance with the Change Compensation Principles.