26.15  Acceleration by Project Co

If Project Co chooses to compress the Development Activities or otherwise accelerate progress other than in accordance with a direction of the State under clause 26.19:

(a)  (no State action): the State will not be obliged to take any action to assist or enable Project Co to achieve any particular sequencing or rate of progress of the Project Activities; and

(b)  (State obligations not affected): the time for the carrying out of the State's obligations will not be affected.