26.20  State's rights and Project Co's obligations and liabilities not affected and time not at large

The State's rights and Project Co's liabilities for any failure by Project Co to achieve Acceptance by the relevant Date for Acceptance as set out in this Deed are not limited or affected by:

(a)  (acceleration): the giving of any Change Response, to accelerate under clause 26.19; or 

(b)  (other circumstances): any:

(i)  breach of any State Project Document by the State;

(ii)  Modification directed or Modification Order issued by the State or the State Representative;

(iii)  other act or omission of the State, any State Associate or any Interface Party;

(iv)  failure by the Independent Reviewer to grant any extension of time under clause 26.9 or to do so within the time required by that clause; or

(v)  other default, act or omission of the Independent Reviewer or any of its Associates,

and none of the matters mentioned in this clause 26.20 will set a Date for Acceptance or any other time at large.