To the extent that Project Co is granted relief under clause 32.2 or clause 32.3 in respect of an Intervening Event that is a Compensable Intervening Event or a Force Majeure Event and, without limiting clause 32.4(b), Project Co or the State will be entitled to claim:
(a) if the Intervening Event is a Compensable Intervening Event, compensation as set out in Item 6 of Table 1 of the Change Compensation Principles; or
(b) if the Intervening Event is a Force Majeure Event, compensation as set out in Item 7 of Table 1 of the Change Compensation Principles,
which will be calculated and determined in accordance with the Change Compensation Principles, except to the extent that the Compensable Intervening Event or Force Majeure Event has given rise to loss or damage to the Project Assets and clause 42.4 or clause 42.5 applies, in which case, Project Co's entitlement to claim any compensation will be as set out in clause 42.4 or clause 42.5 (as the case may be).