32.7  Alternative arrangements

(a)  (Alternative arrangements or method): Without limiting clause 38, if an Intervening Event occurs during the Operational Phase, the State may as a consequence of and for the duration of the Intervening Event or its consequences:

(i)  make alternative arrangements for the performance of those Services or other obligations under this Deed (which are not Development Activities) at no cost to Project Co and without the State incurring any Liability to Project Co in respect of those alternative arrangements; or

(ii)  direct Project Co to:

A.  perform those Services or those other obligations (which are not Development Activities) by an alternative method or "work around" from that contemplated in the then current Operational Phase Plans and the PSDR to the extent that it is reasonably possible for Project Co to do so; or

B.  require Project Co to perform additional Services,

(Work Around).

(b)  (Compensation): If the State Representative requires Project Co to perform a Work Around, this will constitute a Change Compensation Event and Project Co will be entitled to claim compensation as set out in Item 8 of Table 1 of the Change Compensation Principles, which will be calculated and determined in accordance with the Change Compensation Principles.