35.2  Modification Proposal

(a)  (Change Notice): Subject to clause 35.2(b), as a condition precedent to its entitlement to compensation, Project Co must submit a Change Notice to the State entitled "Modification Proposal" in accordance with the Change Compensation Principles for:

(i)  a Modification the subject of a Modification Request issued under clause 35.1, within 20 Business Days after the receipt of the Modification Request, unless the State withdraws that Modification Request prior to the expiry of the time period within which Project Co must submit a Change Notice under this clause 35.2(a), in which case Project Co will not be entitled to make any Claim in respect of the Modification;

(ii)  a State Approval Event, within 20 Business Days after the State Approval Event occurs;

(iii)  a Contamination Compensation Event, within 20 Business Days after a notice under clause 11.6(b) in respect of the Contamination Compensation Event;

(iv)  a Compensable Change in Mandatory Requirements within 20 Business Days after issuing a notice under clause 36.1(a) in respect of the Compensable Change in Mandatory Requirements;

(v)  any loss or damage to Project Assets where clause 42.4(a) or clause 42.4(b) applies, within 20 Business Days after receipt of the State's direction to repair or reinstate under clause 42.2(b)(iii); or

(vi)  any loss or damage to the Project Assets where clause 42.5(b)(ii) applies, within 20 Business Days after receipt of the State's direction to repair or reinstate under clause 42.2(b)(iv),

or such longer period determined by the State in accordance with clause 35.2(b).

(b)  (Extension): If the size and complexity of the proposed Modification and the information to be included in the Modification Proposal, is such that it is not reasonably practicable for Project Co to prepare the Modification Proposal within the period referred to in clause 35.2(a), the State must, on the request of Project Co, extend the date for submitting the Modification Proposal by a reasonable period of time.