36.2  Compensable Change in Mandatory Requirements

(a)  (Compensable Change in Mandatory Requirements): If a Compensable Change in Mandatory Requirements occurs, it will be deemed to be a Modification and:

(i)  Project Co may submit a Modification Proposal in accordance with clause 35.2(a)(iv); and 

(ii)  Project Co's entitlements will be determined in accordance with clause 35.

(b)  (Conditions for Project Co Claim): Project Co is not entitled to make any Claim against the State in respect of any Compensable Change in Mandatory Requirements (including its impact) unless it has given notice in accordance with clauses 36.1(a) and 35.2(a)(iv).