4.1  General

(a)  Project Co's or the State's entitlement to compensation for a Change Compensation Event (as applicable) that occurs during the Operational Phase and the amount of entitlement will depend on:

(i)  the type of Change Compensation Event that has occurred;

(ii)  the nature of the costs that will be incurred by Project Co as a consequence of the Change Compensation Event - capital or recurrent; 

(iii)  the actual consequences of that Change Compensation Event (for example, whether the Change Compensation Event results in additional Costs or Savings being incurred during Operational Phase); and

(iv)  when the Change Compensation Event occurs, in particular before or after Final Acceptance where it is an Extension Event.

(b)  Those Change Compensation Events that may occur during the Operational Phase for which Project Co is entitled to compensation, together with the components of such compensation are set out in Table 1.

(c)  Subject to section 7.2(i), Project Co is only entitled to be compensated, including for any Base Costs, Operational Phase Force Majeure Event Costs, Prolongation Costs, Margin or Agreed Margin for a Change Compensation Event that occurs during the Operational Phase to the extent that Base Costs, Operational Phase Force Majeure Event Costs, Prolongation Costs or Agreed Margin are identified as being payable for the relevant Change Compensation Event in Table 1.