| Section 1 - Details of relevant Change Compensation Event | |
| The relevant Change Notice Event is: | • [insert details eg. Contamination Compensation Event (clauses 11.6, 11.7 and 35 of the Project Deed)] |
| The impact of the Change Notice Event is: | [insert detailed particulars of the nature, occurrence and impact of the relevant Change Notice Event, including: |
|
| • the basis on which Project Co has formed the opinion that an event constitutes a Change Notice Event or it is otherwise entitled to submit a Change Notice for the Change Notice Event; |
|
| • an estimate of the time (if any) during which Project Co will be prevented from carrying out or be delayed in carrying out the obligations affected by the relevant Change Notice Event; |
|
| • in the case of a Change Notice Event which is a Modification the subject of a Modification Order, the time it will take to complete the Modification and the period by which (if any) it will delay Acceptance.] |
| The following information reasonably required by a Change Notice Recipient to demonstrate that Project Co has satisfied the conditions relevant to its Claim in relation to a Change Compensation Event. | [insert details] |
| The following additional information is required under the Project Deed in respect of the relevant Change Notice Event by a Change Notice Recipient and is not otherwise covered in sections 2 to 7 of this Change Notice. | [insert details] |