Section 5 - Details of time implications

The delay is:

[insert details]

The time consequences of the Change Notice Event are:

[insert details, including any impact on any Provisional Acceptance Date, any Date for Commercial Acceptance or any Date for Final Acceptance, any impact on activities on the critical path contained in the then current Development Phase Program and the time during which Project Co will be unable to carry out any other obligations due to the relevant Change Compensation Event]

The number of days extension claimed is:

[insert details]

The basis for calculating the total number of days claimed is:

[insert details]

The following information reasonably required by a Change Notice Recipient to demonstrate that Project Co has satisfied the conditions relevant to its extension of time claim as referred to in clauses 26.8(a) or clause 35.8(c) of the Project Deed (if applicable):

[insert details]

The proposed revised Date for Acceptance:

[insert details]

The following information reasonably required by a Change Notice Recipient to demonstrate whether and to what extent that an acceleration is reasonably achievable under clause 26.17(a) of the Project Deed (if applicable):

The amount of Development Phase Finance Interest:

[insert details]

The amount of Prolongation Costs:

[insert details]