If the State or Project Co terminates this Deed due to a Force Majeure Termination Event and a Default Termination Event is then subsisting, this section 6 will not apply and the Termination Payment will be an amount calculated in accordance with the provisions of section 3 or (if required by section 3) the provisions of section 4.