(a) The State may at any time issue to Project Co a notice entitled "Statement of Proposed Augmentation" which must set out high level details of the proposed Augmentation, and may include (to the extent developed at that time):
(i) a description of the proposed Augmentation (including its unique characteristics and reasons for the proposed Augmentation);
(ii) desired timeframes for the delivery of the proposed Augmentation; and
(iii) any other information considered relevant by the State,
(together the Statement of Proposed Augmentation).
(b) Following the issue of a Statement of Proposed Augmentation, the State may require Project Co to:
(i) submit an initial response to the Statement of Proposed Augmentation which sets out any key issues or risks that Project Co considers may arise in respect of the proposed Augmentation, within the period reasonably specified by the State in the Statement of Proposed Augmentation; and
(ii) enter into, and procure that:
A. the Proponents; and
B. those Project Co Associates and Proponent Associates (as reasonably nominated by the State),
enter into, a deed substantially in the form of the Probity and Process Deed within 10 Business Days of any such request by the State.