(a) The Augmentation Process Deed will specify agreed milestones in order to achieve Contract Close by the Date for Contract Close (each a Milestone and together the Milestones).
(b) The Proponents and the State may agree that, on the achievement of certain Milestones, the Proponent will be entitled to payment of Third Party Costs in accordance with the principles set out in section 9.
(c) The Augmentation Process Deed may require the Proponents to:
(i) achieve Milestones by a specified date; or
(ii) use their best endeavours to achieve Milestones by a specified date,
depending on the nature of the Milestone and the importance of timing in the context of the Augmentation.
(d) The Augmentation Process Deed should include a Date for Contract Close as a Milestone.