Interface Management Strategy

Guidance note: The Proposal Requirement should be updated to include any additional key interfaces.  The Interface Management Strategy is to be consistent with Proposal Requirements A5 (Interface Management) insofar as it relates to the interface management issues during the Development Phase.

Respondents are required to provide an Interface Management Strategy that sets out Project Co's understanding of, and approach to, managing interfaces, including:

•  intra-consortium interfaces between Project Co and Respondent Members so as to provide a fully integrated approach to delivering the Project;

•  [Insert Procuring Agency] (including the State Representative) and the State more generally; 

•  Project Stakeholders and the community; and

•  the commercial impact of Project interfaces.