Guidance note: Procuring Agencies should consider specifying an appropriate maximum fixed percentage for the Agreed Margins in Table 12 and Table 13. Procuring Agencies should note that the dollar thresholds in Table 13 (Agreed Margins for Change Compensation Events that occur during the Operating Phase) should be interpreted as an average per annum over those years for which there is a cost impact and the cost amounts should be considered without any savings. Higher dollar thresholds may be appropriate where a project is a full service PPP and should be considered on a project-specific basis in consultation with the Department of Treasury and Finance. Where the Project is a full service PPP (i.e. provision of additional ancillary and operational services), the Proposal Requirement should be updated to reflect this model. |
Respondents are required to tender maximum fixed percentages for Agreed Margins for Change Compensation Events that occur during the Development Phase and the Operating Phase that have not been hard coded in:
• Table 12 (Agreed Margins for Change Compensation Events that occur during the Development Phase); and
• Table 13 (Agreed Margins for Change Compensation Events that occur during the Operating Phase).
Table 12: Agreed Margins for Change Compensation Events that occur during the Development Phase
Relevant Margin | Applicable Fixed Percentage | ||
$0 to $1m | >$1m to $5m | >$5m | |
[Bid amount]% | [Bid amount]% | [Bid amount]% | |
[Bid amount]% | [Bid amount]% | [Bid amount]% | |
0% | 0% | [Bid amount]% | |
Table 13: Agreed Margins for Change Compensation Events that occur during the Operating Phase
Relevant Margin | Applicable Fixed Percentage | ||
$0 to $1m | >$1m to $5m | >$5m | |
[Bid amount]% | [Bid amount]% | [Bid amount]% | |
B. Construction Margin of Services Contractor or D&C Contractor | Same as Construction Margin of D&C Contractor in Table 12 | Same as Construction Margin of D&C Contractor in Table 12 | Same as Construction Margin of D&C Contractor in Table 12 |
0% | 0% | [Bid amount]% | |
Note that the agreed fixed percentages for the Agreed Margins will be incorporated into Schedule 5 (Change Compensation Principles Schedule) of the Project Deed.