The Crossrail funding and financing model

Figure 6 Breakdown of contributions to the Crossrail funding package of £17.6 billion

Notes

1  Cost in £ millions, includes £750 million contingency loan announced in December 2018. Excludes the cost of the rolling stock and depot.

2  GLA = Greater London Authority;

DfT = Department for Transport,

TfL = Transport for London;

NR = Network Rail;

HAL = Heathrow Airport Limited.

3  Precise levels of funding from some sources, such as sale of surplus land and property may be subject to change.

Source: National Audit Office analysis of departmental information