Progress against the timetable for opening the railway

The Department and TfL originally planned for the central section of the railway to start running from December 2018. In 2010, sponsors decided to stagger the opening of the railway by opening the railway in sections and introducing services in a phased way. This was in order to reduce risks - and therefore reduce the costs allocated to risks - associated with opening the railway 'all at once'.

As Figure 14 on the right shows, Crossrail Ltd did not open the full, planned services for stages 1 and 2 on time, and it remains unclear when stages 3, 4 and 5 will open. New class 345 Bombardier trains are in use between Shenfield and Liverpool Street as part of the opening of stage 1 services, but are not yet in use between Heathrow and Paddington as had been planned. This is because the software required to use the ETCS signalling system that is on the line into Heathrow has not yet been successfully implemented and tested.

Project sponsors have agreed a concession arrangement with Mass Transit Railway (MTR) to operate the new railway. MTR are paid a performance-related fee for operating the railway, with TfL retaining revenues. Because of the delays to opening the railway, TfL's revenues will not start to increase significantly until stage 5 is complete and full end-to-end journeys through central London are possible. TfL's December 2018 business plan states that its revenues could be around £600 million lower than expected as a result of delays to the opening of Crossrail services. Because Crossrail Ltd and sponsors have not yet confirmed the opening dates for stages 3, 4 and 5, these estimates remain uncertain.

Crossrail Ltd is currently developing a new schedule for the programme.

Figure 14 Current plans for introducing new Elizabeth line services

Stage

Description

Target date

Actual/
forecast delivery

1

Liverpool Street (main line) to Shenfield

May 2017

June 2017

2

Heathrow to Paddington (main line)

May 2018

Stage 2 opening partially achieved in May 2018. Two Class 345 trains per hour are running from Paddington to Hayes and Harlington, rather than four trains per hour to Heathrow as planned. The Department currently expects four trains per hour to be running by December 2019

3

Paddington (Crossrail) to Abbey Wood - using new Class 345 trains with 15 trains per hour

December 2018

Unknown

4

Paddington (Crossrail) to Shenfield - using new Class 345 trains with 12 trains per hour

May 2019

Unknown - dependent on stage 3

5

Full east-west service with 24 trains per hour in each direction

December 2019

Unknown - dependent on stage 3. There are currently plans to introduce some Crossrail services between the existing Paddington station and Reading from December 2019

Source: National Audit Office analysis of departmental information