4. KRIAN - LEGUNDI - BUNDER - MANYAR TOLL ROAD

LOCATION : East Java

Sector : Road

Sub-Sector : Toll Road



Description:

Part of the Trans-Java Toll Road located in East Java with length at approximately 38.2 km from Krian to Manyar. One of the attractive points for development of this toll road is that it will have tremendous facilities, such as development of residential areas and commercial areas along the corridor.

Estimated Project Cost : USD 940.0 Milion

Financial Feasibility:

FIRR : 14.60%

NPV : USD 287.0 Milion

Estimated Concession Period : 45 Years

Government Contracting Agency

: Indonesia Toll Road Authority ("BPJT") On Behalf of Ministry of Public Works and Housing

Contact Person

: Mr. Herry Trisaputra Zuna (Head of BPJT) +62-21-7258063; e-mail: bpjt@pu.go.id or investasi2.bpjt@gmail.com

Project Status:

Project is currently on under construction (land acquisition stage)

Toll Road Company: PT. Waskita Bumi Wlra

1. PT Waskita Toll Road;

2. PT Energi Bumi Mining;

3. PT Panca Wira Usaha Jawa Timur.

Financier :

Financial close through Contractor Pre-Financing (CPF)

Indicative Government Support & Guarantee: Necessity :

project's authorization risk, construction delay risk, payment risk and guarantee statement from Government

Implementation Schedule (Estimated):

1. Preparation

: 2015

2. Land Acquisition

: 2016

3. Construction

: 2016 - 2018

4. Operation

: 2019