LOCATION: Medan City
| Sector: Transportation | Sub-Sector: Railway | |
|
| Description: The LRT system is planned to be built with elevated structures connecting the urban sub-centers of Lau Chi Market in the Southwest of Medan with sub-city centers in the northeastern part of Medan City along 21 km and through 16 stations. BRT system will cross Jalan Sisingamaraja to Jalan Gatot Subroto with a length of 18.4 km. Estimated Project Cost : USD 353.0 Million Financial Feasibility: FIRR : 14.46% NPV : USD 293.4 Million Estimated Concession Period : 35 Years |
| Government Contracting Agency | : Mayor Of Medan |
| Contact Person | : Mr. Wiriya Alrachman (Head of Regional Planning and Development Agency) +62-61-4535774; e-mail: bappedamedan@gmail.com |
| Indicative Preparation Schedule (Estimated) |
|
Project Status: The project is currently on Final Business Case phase. |
| Indicative Project Structure |
|
|