In SPAM Pekanbaru, initial identification of the project development intake location, transmission pipeline, reservoir, and distribution pipeline network is as follows:
a. Intake location
Intake is planned to be built in a 'tampan' area located on the banks of the Siak River.
b. Transmission pipeline plan
Transmission pipeline is planned to be built on several roads.Related to that issue based on information from the Regional Finance and Asset Management Board of Pekanbaru, the road status is planned to be used as the location of the transmission pipeline network.
c. Reservoir plan
The reservoir is planned to be built in 4 (four) areas which are: Payung Sekaki sub-district, Sukajadi sub-district, Sail sub-district, and Lima Puluh sub-district. Related to the information obtained from the Regional Financial and Asset Management Division of Pekanbaru, the status of land to be used for the construction site of the reservoir in the Pekanbaru SPAM Project.