7.  Project Structure

DFB and M

Estimated project cost

USD 176.5 Million

Indicative debt to equity

 

- Debt Level

70%

- Equity Level

30%

FIRR

14.00%

Basic Assumptions of the National Integrated Welfare System project:

No.

Investment loan liabilities

 

Per year, (BI, average interest scheme 2011-2017)

1

Lease Loan Agreement

7.5%

Per year

2

The inflation rate begins in 2019

4.5%

Per year

3

Investment loan period

12

Year

4

Loan Leasing Period

15

Year

5

Duration Availability Payment (AP)

20

Year

6

Grace periode

2

Year

7

Leasing value

IDR 500

Million

8

Return On Investment Rate AP

14%

 

9

Discount factor

10%

 

10

% increase tariff

10%

Every 3 years

11.

Factorial price (category)

5

level

12.

Private equity

30%

 

13.

Bank Loan

70%

 

14.

Interest during construction

10%

 

15.

Financial fees

1.50%

 

16.

Corporate Income Tax

25%

Surplus BUP