CHAPTER 3 Routine Contract Management
>
3.1 Managing transitions
>
3.1.2 Construction to operations
>
GUIDANCE
GUIDANCE
More Information
A. Ensure adequate resourcing is employed for to testing and commissioning
B. Plan for testing and commissioning early, and consider establishing a testing and commissioning panel
C. Allow adequate time for the parties to become familiar with the operational Key Performance Indicators and payment mechanisms
D. Focus on the relationship with the Project Company during the transition between construction and operations, and mitigate the risk of disputes