D. Agree the level of detail required from the Project Company early, to set expectations around the form of information required

The contractual requirements of the information management system do not always specify the level of detail required, which is important from an operational point of view. This can be problematic when it is not clear what is required. The Procuring Authority should agree what is required from the Project Company from the outset of each project phase, as the level of detail may not be prescribed in the PPP contract.