Claims for the Procuring Authority's breach of contract

An issue of Procuring Authority non-compliance or breach of the PPP contract which negatively affects the Project Company's ability to deliver its works or services will typically lead to a claim for additional time and costs. When a breach of a contract is defined as a default, then it could give also rise to termination rights. For example, failure to provide land or access to a site on time, failure to make a payment on time, failure to execute third party agreements on time, failure to secure relevant approvals, or failure to deliver interfacing infrastructure. Other actions that negatively affect the Project Company's ability to deliver its works or services can also lead to a right to claim.