2  Procuring Authority team data

Table 1: Prevalence of use of Contract Management Manual by region

Region

No. of Projects with data

No. of Projects with Contract Management Manual

% of Projects with Contract Management Manual

Africa

3

1

33%

ANZ

3

3

100%

East Asia

6

1

17%

Europe

35

12

34%

Latin America and the Caribbean

33

0

0%

MENA

7

1

14%

North America

5

4

80%

SE Asia

5

0

0%

South Asia

16

11

69%

TOTAL

113

33

29%

Our research shows that there is no set formula for the size and structure of the Procuring Authority team; it can vary from a couple of individuals up to over 50 depending on the complexity of the PPP contract and the type of involvement the Procuring Authority wishes to have. However, it is common for the team to be made up of only a small number of permanent staff (i.e. less than ten, and often less than five), and for external advisors and contractors to be used as necessary. A number of stakeholders interviewed perceived their teams as short staffed, but did not feel that the size of the team hampered effective contract management.