The Grid Operator was involved in the commissioning of the substation, and was responsible for ensuring compliance by the Project Company with the Grid Operator's specifications and procedures. This is to protect the grid from damage and facilitate a smooth integration into the grid, as well as guaranteeing safe operation during the PPP contract period. The owner of the high-voltage transmission line was also involved in the testing and commissioning of the project.
No issues or disputes were faced during the testing and commissioning of the substation. The process was smooth and final approval was given by the Procuring Authority and Grid Operator to start commercial operation in July 2015.