The Procuring Authority's more active role in the monitoring of the project ends with the commissioning phase. Its role in the monitoring of the project is then scaled back to an oversight role whereby the Procuring Authority intervenes only if and when necessary. When the transmission line entered into service, the Grid Operator took over from the Procuring Authority the performance monitoring of the Project Company. The operation is monitored in real time and the associated performance monitoring reports are made available on the public domain.