Right of Way can be a major challenge for transmission line projects such as this one. In order to address this challenge, the government provides procuring authorities with the administrative power to expropriate land for public utilities, if necessary. The relevant law facilitates Right of Way for the purpose of the utility project, preventing unnecessary delays to the project and other projects considered necessary to provide a public service. Ownership of the land is maintained by the previous owner, and payment for this right with some use restrictions is approximately 30% of the value of the land. The Project Company is required to purchase land needed for the substations only.