The Daang Hari-SLEX Link Road, locally known as Muntinlupa-Cavite Expressway, is a 4km 4-lane toll road project. The project is a build-transfer-operate PPP and has been operational since 24 July 2015 with no material issues during the operations phase. The challenges faced in this project started early in the construction phase, where a variation had to be introduced to ensure its success. In addition to the variation, challenges were faced in acquiring land for the project, causing delays in the construction phase. The effectiveness of the parties in dealing with these challenges highlights the benefits of effective contract management in infrastructure projects. This case study is also an example of the positive role PPP units can have in advising procuring authorities. At the time of conducting this case study, the Daang Hari-SLEX Link Road project has been operational for two years.