The PPP contract is for 30 years and has a provision allowing for an extension of up to 20 years (50 years in total from commencement of construction). According to the Procuring Authority, the objectives of the project were to benefit commuters, motorists and the general public, and to deliver strategic benefits to the region such as:
• Providing an alternative route to/from Metro Manila/Cavite
• Improving the regions' competitiveness as an investment destination
• Decongestion of the traffic in Cavite, Las Piñas, and Muntinlupa
• Reducing travel time by an average of 45 minutes from Daang Hari to Alabang Interchange
• Providing new access to the National Bilibid Prison (NBP) property, which is intended to be redeveloped into a mixed commercial, residential, and institutional estate