Information Management

The Procuring Authority has not prescribed an information and data management system. The Project Company submits reports via email in advance of monthly review meetings. There was a shared data management system used during the design phase, as well as a shared risk register, however this was done for practical reasons rather than as a strict requirement. This has allowed the parties to adapt their working styles to the circumstances.