PSC is derived from the monetisation of the following factors:
1. Raw PSC (also referred as Whole of Life Cycle Cost)
2. Competitive neutrality
3. Retained Risk
4. Transferable Risk

PSC is calculated as the net present value (NPV) of a projected cash flow based on the appropriate discount rate for the public sector.