| NO | ASPECTS | DESCRIPTION |
| 4. | Available Sectors | 1) Education; 2) Health; 3) Infrastructure; and 4) Services. |
| 5. | Eligible Tender Participants / Project Initiator | 1) Strong technical and financial capabilities; and 2) Relevant expertise to manage and maintain the asset. |
| 6. | Types of PPP Structures/ Contract Types | 1) Build-Lease-Maintain-Transfer (BLMT); 2) Land Swap/Joint Venture (JV); 3) Build-Operate-Transfer (BOT); 4) Build-Lease-Transfer (BLT); 5) Build-Operate-Own (BOO); 6) Management Contract; 7) Sale of Assets and Equity; and 8) Corporatisation. |
| 7. | Types of Project | 1) Projects initiated by the private sector (unsolicited proposals); and 2) Projects initiated by the government (solicited proposals). |
| 8. | Project Stages and Implementation for Solicited Proposals | 1) Submission of PPP proposals from the ministries/agencies 2) Evaluation of PPP proposal and submission to Cabinet for approval in principle 3) Ministries/agencies/PPP Unit prepare bidding document and undertake invitation to bidders 4) PPP Committee to evaluate and endorse the preferred bidder 5) Approval in principle from the Cabinet for the selection of the preferred bidder 6) Value management lab for detailed technical specifications and finalising costing 7) Negotiation of terms and conditions with the selected company (may occur concurrently with value management lab) 8) Memorandum to the Cabinet on finalised terms and conditions 9) Signing of PPP agreement 10) Project implementation |
| 9. | Project Stages and Implementation for Unsolicited Proposals | 1) Submission of PPP proposals from the private sector 2) Evaluation of PPP proposals and submission to Cabinet for approval in principle 3) Approval in principle from the Cabinet for the selection of the company 4) Value management lab for detailed technical specifications and finalising costing 5) Negotiation of terms and conditions with the selected company 6) Memorandum to the Cabinet on finalised terms and conditions 7) Signing of PPP agreement 8) Project implementation |
| 10. | Mechanisms to Engage Private Sector at Project Development Stages | Private sector is engaged at project development stage through value management lab in which the need and scope of project are discussed briefly between private and the government. |
| 11. | Project Appraisal and Selection Process | A PPP proposal will only be considered if there is a need on the part of the government for the project after taking into account the benefits as a whole in terms of, inter alia: 1) Socio-economic impacts; 2) Value for money and cost savings to the government; 3) Quick delivery of the project and service enhancement; and 4) Increased level of accountability, efficiency and effectiveness. |