Section 10: Written Comments on RFP documentation

The Work Team may also accept written comments on the draft RFP documentation, including the draft Privatization contract. If this will be done, the process for submitting comments shall be clearly set out in the RFP, including a clear timetable for asking such clarifications. Responses to comments shall be provided to all bidders, to ensure that all bidders have access to equal information. Note that multiple rounds of clarifications and responses may be conducted.