To be considered timely, a compliant appeal must be received by the procuring Entity within the following time limits:
a) For an appeal of the selection of preferred bidder, the appeal must be received by the Privatization Procurement Appeals Board within 10 working days of publication of notice of preferred bidder on the procuring Entity's website.
b) For an appeal of the shortlist selection of preferred bidder, the appeal must be received by the Privatization Procurement Appeals Board within 10 working days of publication of notice of shortlist on the procuring Entity's website.
c) For an appeal of the RFQ or RFP bidding requirements, the appeal must be received by the Privatization Procurement Appeals Board prior to the closing date for RFQ or RFP responses.