3.2.38 The requirement to publish the schedule of tenders on GeBIZ not later than three working days after the tender closing date applies.
3.2.39 The ultimate aim of the evaluation process is to select the PPP provider who is best able to manage and deliver the project. The GPE must evaluate tender proposals using the evaluation model or criteria set forth in the ITT. The GPE must not at this junction change criteria or waive essential requirements or contractual terms after the closing of the tender.