Annex A5: Uncertainty, Optimism Bias and Risk

A5.1 This Annex covers the Green Book approach to uncertainty, optimism bias and risk, covering:

  definitions

  adjusting for optimism bias

  risk quantification

  risk management and categories of risk

  the interaction between risk and optimism bias

  reducing optimism bias

  project or programme contingency and optimism bias

  presentation of optimism bias in appraisal results

A5.2 The focus is on the application of optimism bias and quantification of risk, in the context of uncertainty about costs, benefits and time taken to deliver interventions. The approach set out here primarily applies to the appraisal and management of projects and programmes, usually associated with new public spending, but the principles are applicable to government appraisal more widely. Green Book supplementary guidance provides more information on the treatment of uncertainty and risk when valuing infrastructure.

More Information